- Stripping grass and topsoil
- Bulk excavation and bulk fill under level 1 GITA supervision
- Compaction to AS3798
- Sleeper retaining wall construction
- Road works along Heaslip Road DIT road, including water and sewer connections
- Construction of 4m deep sewer including chambers
- Construction of stormwater, water, CST, electrical and NBN
- Installation of kerbing, kerb outlets, asphalt and linemarking
- Construction of pedestrian footpath with exposed concrete