- Detailed traffic management
- Demolition of 10,000m2 carpark
- Demolition of trees, kerbs and underground infrastructure
- Construction of piling pads and providing edge protection battering
- Construction of 3m high precast exposed retaining walls
- Backfill with agi pipe and screenings of precast walls
- Carpark preparation and road works into DIT road
- Deep stormwater construction
- Kerbing, pavement construction and asphalt works